Dapeng Town Industrial Park, Tongshan District, Xuzhou City, Jiangsu Province, China
80% of production can be finished at factory
Easy and fast installation
Cost-effective
High security
Roof and side enclosures can be installed on the ground and lifted successfully once
This project used four square quadrangle welding ball node space truss structure, to find all around structure slope plate rack, rack using peripheral bottom chord bearing in elevation is + 12.2 m concrete pillars, rack maximum altitude + 18 m, spatial vector level 2500-4200 – mm, station building second floor elevation + / – 0.00 m, stilt floor elevation of 5.50 m, Highway station adopted “ground assembling + around ascending simultaneously support bracket in the whole sealing side” of the construction plan.