Dapeng Town Industrial Park, Tongshan District, Xuzhou City, Jiangsu Province, China
Construction sequence of space frame glass roof:
Roof space frame installation → purlin laying → positioning → sticking adhesive strips → laying glass lap → edge installation
The operation steps are as follows:
Glass laying: In order to speed up the glass installation progress and enhance the sense of security of workers, after the glass reaches the space frame, the glass is spread out according to the sequence and direction of its installation, and number the different glass in each area to avoid difficulty in finding due to too many types of glass. Reserve the position of the first piece of glass to be installed when laying glass, The upper, lower, left and right sides of the glass should fall on the rubber strip on the purlin, and then seal and glue. Operators can stand on the glass to operate. Positioning and fastening glass: lap joint and edge closing installation according to the operation manual.
We SAFS have more than 20 years of experience, a professional space framed glass roof design and installation company.
Glass roofing is applicable to a wide range of areas: church roofing, shopping center hall, art exhibition hall, reception hall and so on. If you need it, please contact me on the home page.